The Ministry of Industry and Trade proposes that EVN urgently unify the price of solar power and transitional wind power

The Ministry of Industry and Trade has just directed EVN to urgently coordinate with investors of solar and wind power plants to negotiate and unify electricity prices.

Specifically, the Ministry of Industry and Trade has just issued Official Dispatch No. 094/BCT-ĐTL urgently to the Electricity of Vietnam (EVN) on negotiating electricity prices for solar and transitional wind power plants.

Previously, the Ministry of Industry and Trade issued Decision No. 21/QD-BCT promulgating the price bracket for electricity generation of solar power plants and transitional wind power plants.

Accordingly, the ceiling price (the highest price) of the electricity generation price bracket (excluding value added tax) applied to ground solar power plants is 1,184.90 VND/kWh, floating solar power is 1,508 .27 VND/kWh, inland wind power is 1,587.12 VND/kWh, sea wind power is 1,815.95 VND/kWh.

This power generation price framework is the basis for EVN to negotiate the purchase price of electricity from transitional and commercial renewable energy plants after more than 2 years of waiting, since the FIT price (supported electricity tariff) is preferred. offer expires.

To come to an agreement, the Ministry of Industry and Trade made three requirements in the principle of determining electricity generation prices. That is, must comply with the provisions in Clause 1, Article 29 of the Electricity Law on electricity price policy; in which, the Ministry of Industry and Trade emphasized, it is necessary to create conditions for all economic sectors to invest in electricity development with reasonable profits.

According to the provisions of Clause 4, Article 29 of the Electricity Law, the Ministry of Industry and Trade requires "Ensure the right to self-determination of electricity buying and selling prices within the price bracket and structure of the electricity retail price schedule prescribed by the State of the subjects of electricity purchase and sale. buying and selling electricity on the electricity market".

Another principle is "The electricity generation price according to the definite-term electricity purchase and sale contract, the wholesale electricity price agreed upon by the electricity units but must not exceed the electricity generation price bracket, the electricity wholesale price bracket approved by the Government. ", as prescribed in Clause 3, Article 31 of the Electricity Law.

Regarding the power purchase and sale contract, the Ministry of Industry and Trade stated that the investor and EVN negotiate and amend on the basis of the signed power purchase and sale contract and the contents specified in Circular No. 01 (January 19, 2020). 2023) abolishing a number of regulations in Circular 02 (January 15, 2019) and Circular No. 18 of the Minister of Industry and Trade…

With the above requirements, the Ministry of Industry and Trade asked EVN to urgently coordinate with investors of solar and wind power plants to forward agreement and unify electricity prices.

Currently, among the projects waiting for a new electricity price bracket, there are 5 solar power projects or parts with a total capacity of more than 452 MW awaiting determination of electricity prices and 62 wind power projects with a total capacity of nearly 3,480 MW has signed a power purchase agreement with EVN. In addition, there are a number of projects that are under investment and in progress, and are also waiting for the transitional price mechanism and price to negotiate prices and power purchase and sale contracts with EVN.

If electricity prices are applied, the future of clean electric energy industries will develop because Vietnam has a lot of potential in solar and wind energy. Euro Construction Systems Co., Ltd. provides a combo of anti-slip system on the roof and solar batteries. We will design an anti-slip system that runs around the area where the solar panels are installed and the roof is installed to ensure the safety of people installing, inspecting, maintaining or repairing the roof or solar panels. solar quantity.

Why should you choose to buy a combo of solar batteries and Eurocs anti-slip system?

1. Free consultation and design installation location for customers

2. Save time and management costs: Instead of you having to find two separate units to supply and install solar panels and anti-slip systems, just choose Eurocs and we will doing the work package of those two units, this will help you manage and track the work easily.

3. Eurocs products have been tested with a load capacity of 200 kg.

Contact 0971 594 488 or visit website: www.eurocs.com.vn for advice and support.

Xem thêm: Nguyên tắc đảm bảo án toàn khi lắp đặt pin năng lượng mặt trời trên mái nhà